Alliance Street Mill And Overlay Project Begins Monday

The Alliance Street Mill and Overlay project will begin Monday, June 5.  Please remove all items from the street to allow crews clear access.  Simon Contractors will be installing “No Parking” signs in each of the locations two days prior to construction.  The streets will be closed during the milling process and then again during the overlay process.  Streets will reopen for use between the milling process and the overlay process.  The anticipated completion date is July 2017.

 

The project will include the following locations and will move in the order listed:

 

West 8th Black Hills to Colorado

West 7th Emerson to Platte           

West 5th Laramie to Big Horn

4th Street from Emerson Avenue to Box Butte Avenue

Laramie Avenue from 4th Street to 10th Street

West 12th Laramie to Box Butte

2nd Street from Niobrara Avenue to Potash Avenue

2nd Street between Niobrara and Box Butte Avenue

Niobrara Avenue from 3rd Street to 10th Street

Parking lot at 4th and Niobrara

Sweetwater Avenue from 3rd Street to 8th Street

Sweetwater Avenue 300′ south of 4th Street           

Yellowstone Avenue from 3rd Street to 8th Street           

Mississippi Avenue from 2nd Street to 10th Street

Anthony Avenue West 4th to West 6th

West 21st Street from Box Butte Avenue west 500 feet

Peterson Court

Emerson Avenue from 25th Street to north of 31st Street

 